Working days calculator

Count the working days between two dates on a standard Monday to Friday week, excluding any holiday dates you enter.

Calculator

The first day of the interval. A same-date interval counts zero days.

The day after the last day counted, so the interval is start included, end excluded.

Up to three observed holiday dates. Duplicates, weekend dates and dates outside the interval change nothing, so park unused slots on any weekend date.

Up to three observed holiday dates. Duplicates, weekend dates and dates outside the interval change nothing, so park unused slots on any weekend date.

Up to three observed holiday dates. Duplicates, weekend dates and dates outside the interval change nothing, so park unused slots on any weekend date.

Working days
5

Advertisement

How this calculator works

Working days here means calendar weekdays from Monday to Friday. The start date is included and the end date is excluded, so a Monday to the following Monday spans one full working week unless a holiday intervenes. Holidays are the observed dates you supply; no national or provincial calendar is assumed, which keeps the answer honest for shift workers, part-time schedules and cross-border teams.

Formula

For an interval of L calendar days, full weeks contribute 5 each. The leftover r days are checked from the start weekday w, Monday as 0, adding one when (w + j) mod 7 is 0 to 4. Unique weekday holidays inside the interval are then subtracted.

Worked example

From Monday 2026-11-02 to Monday 2026-11-09 is 5 working days. Placing a holiday on Saturday 2026-11-07 leaves the count unchanged.

Advertisement

Frequently asked questions

Does this support a four-day work week?

No. The schedule is fixed at Monday to Friday. A custom schedule would need a different rule for which weekdays count.

Why are weekend holidays ignored?

Weekends are never counted as working days, so subtracting a weekend date would double count the exclusion. Enter the date the holiday was observed if your workplace moved it to a weekday.

Does the result include both the first and last date?

The first date is included and the last date is excluded. Moving the end date forward by one day is the reliable way to include the final date.