Advertisement

Business days calculator

Count weekdays in an interval, with an optional holiday date in each of three slots. Only Monday to Friday count; the end date is excluded.

Calculator

The first day of the interval. A same-date interval counts zero days.

The day after the last day counted, so the interval is start included, end excluded.

Up to three observed holiday dates. Duplicates, weekend dates and dates outside the interval change nothing, so park unused slots on any weekend date.

Up to three observed holiday dates. Duplicates, weekend dates and dates outside the interval change nothing, so park unused slots on any weekend date.

Up to three observed holiday dates. Duplicates, weekend dates and dates outside the interval change nothing, so park unused slots on any weekend date.

Business days
4

Advertisement

How this calculator works

The interval runs from the start date, which is included, up to the end date, which is excluded. Full weeks contribute five weekdays each, and the leftover days are checked one by one. Each unique holiday date that falls on a weekday inside the interval removes one day. Duplicate holidays, weekend holidays and dates outside the interval change nothing, so unused slots can stay on a weekend date.

Formula

Let L = O(end_date) - O(start_date), q = floor(L / 7), r = L mod 7, and w the weekday of the start date with Monday as 0. Start with 5q plus one for each j from 0 to r - 1 where (w + j) mod 7 is below 5. Then subtract each unique holiday in the interval that falls on a weekday.

Worked example

From Monday 2026-06-29 to Monday 2026-07-06, with Canada Day on Wednesday 2026-07-01 supplied as a holiday, gives 4 business days. A same-date interval gives zero.

Advertisement

Frequently asked questions

Are Canadian statutory holidays removed automatically?

No. Federal, provincial and employer schedules differ, so you supply the observed dates yourself. Nothing is inferred from the province or the year.

Why is the end date excluded?

A half-open interval makes chained counts add up cleanly: the end of one period is the start of the next without double counting. If you need both endpoints, choose the following day as the end date.

What happens to a holiday that falls on a weekend?

It subtracts nothing, because weekends are already excluded from the weekday count. Move an observed holiday to the weekday it was actually taken on if that differs.

Sources