Rebar calculator

Count straight runs in a two-way reinforcement grid with an edge offset and maximum spacing. Enter the grid already specified for your slab.

Calculator

Runs parallel to slab length
16
Runs parallel to slab width
21
Total installed bar length
123.3
Minimum purchased stock bars
21
Installed nominal bar mass
96.791
Estimated material cost
$210.00
Straight-run schedule
DirectionRunsLength each (m)
Along length16.0003.900
Along width21.0002.900

Advertisement

How this calculator works

Edge offsets reduce the reinforcement rectangle in both directions. The number of spaces is rounded up so the maximum spacing is not exceeded; adding one gives runs in each direction. Nominal masses follow Gerdau Canadian metric rebar data. Dividing total length by stock length gives a theoretical minimum purchase count, assuming usable offcuts and unrestricted splicing.

Formula

Lgrid = L - 2c; Wgrid = W - 2c; rows = ceil(Wgrid / spacing) + 1; columns = ceil(Lgrid / spacing) + 1; total length = rows x Lgrid + columns x Wgrid; stock bars >= ceil(total length / stock length).

Worked example

A 1 m by 1 m grid at 200 mm spacing with zero edge offset has six runs each way: 12 m total. At 0.785 kg/m, 10M bar weighs 9.42 kg; two 6 m stock bars are the theoretical minimum.

Advertisement

Frequently asked questions

Is the edge offset concrete cover?

The input is to the bar centreline. If a drawing gives clear cover to the steel surface, add half the bar diameter to obtain this offset.

Why might I need more stock bars?

Cutting waste, lap splices, hooks, bends and unusable offcuts can increase the purchase count. This is a straight-length lower bound, not a fabrication schedule.

Does this select bar size or spacing?

No. Those values must come from the slab design. A material takeoff does not check reinforcement capacity or code compliance.